A kitchen remodel involves a series of carefully orchestrated steps that typically take 8-12 weeks from planning to completion. The process includes developing a budget, creating a design, removing the old kitchen, installing new plumbing and electrical, framing, drywall, flooring, cabinets, countertops, appliances, and lighting, followed by final details and cleanup.
Understanding the kitchen remodel process helps you prepare for each phase, manage expectations, and ensure your renovation stays on track and within budget. This comprehensive guide walks you through every step of the kitchen remodeling journey, from initial planning to final walkthrough.
This is the second chapter in our Kitchen Remodeling Guide that contains guidance to help you navigate the entire process.
The kitchen remodel process follows a specific sequence designed to ensure quality workmanship, code compliance, and efficient completion. Each phase builds upon the previous one, making proper planning and sequencing essential for success.
Total Timeline: 8-12 weeks
Key Process Steps:
Understanding this sequence helps you prepare for each phase and avoid costly delays or mistakes that can derail your project timeline and budget. A note that this process will look different based on how you approach your remodel. Learn more about Portland Kitchen Remodeling with Lamont Bros.
Timeline: 2-3 weeks
You may have been thinking about remodeling your kitchen and how you'd like it to look for far longer than 2-3 weeks. If you haven't already, take stock of your current kitchen's strengths and weaknesses.
Document what works well and what needs improvement. Consider storage capacity, workspace efficiency, lighting quality, and traffic flow patterns. This assessment guides your renovation priorities and helps you communicate your needs to designers and contractors.
Chapter One of this guide is all about kitchen design.
Clearly outline your remodeling objectives. Are you updating aesthetics, improving functionality, expanding space, or completing a full renovation? Prioritize your goals to guide decision-making throughout the process. Consider how you use your kitchen daily and what features would improve your cooking and entertaining experience.
Work with a kitchen designer to develop detailed plans including final layout, elevations, material specifications, lighting plans, and plumbing requirements. Professional design ensures proper space planning, code compliance, and efficient workflow patterns.
Design deliverables include:
Create a prioritized list of essential features versus nice-to-have elements. This helps make decisions when budget constraints require compromises. Consider storage needs, appliance requirements, seating areas, and special features like islands or pantries.
Planning a Home Renovation: 5 Key Questions to Ask
Timeline: 1-2 weeks
Establishing a realistic budget early in the process prevents costly changes and ensures your project scope aligns with available resources. Kitchen remodel costs vary significantly based on size, materials, and complexity.
Chapter 3 of our guide is all about kitchen remodel costs.
Timeline: 2-4 weeks in Portland
Most kitchen remodels require building permits to ensure work meets safety codes and local regulations. The permit process protects your investment and ensures proper installation of electrical, plumbing, and structural elements.
Portland requires permits for:
Your contractor typically handles permit applications, which include:
Portland requires multiple inspections throughout the process:
Plan your construction schedule around required inspections to avoid delays. Failed inspections require corrections and re-inspection, which can add weeks to your timeline.
Timeline: 1-2 weeks
Selecting a qualified contractor is crucial for project success. Take time to research candidates thoroughly and verify their credentials, experience, and reputation.
Look for contractors with:
Ask potential contractors:
Ensure your contract includes:
Be wary of contractors who:
Timeline: 6-8 weeks lead time for cabinets
Many kitchen materials require substantial lead times, making early ordering essential for staying on schedule. Create a procurement timeline that ensures everything arrives when needed during construction.
Custom and semi-custom cabinets typically require 6-8 weeks for manufacturing. Place cabinet orders immediately after finalizing design and securing permits. Delays in cabinet delivery can push back your entire project timeline.
Order appliances 4-6 weeks before installation to ensure availability and proper sizing. Coordinate delivery timing with your contractor to avoid storage issues and potential damage.
Plan for these typical lead times:
Schedule deliveries to arrive just before installation to minimize storage needs and reduce damage risk. Your project manager should coordinate all deliveries with the construction schedule.
Timeline: 1-2 weeks
Demolition marks the beginning of active construction. Proper preparation and systematic removal prevent damage to surrounding areas and ensure safe working conditions.
Before demolition begins:
Timeline: 3-5 weeks
Rough construction installs the infrastructure that supports your finished kitchen. This phase requires careful coordination between electrical, plumbing, and HVAC trades.
Complete any structural modifications first:
Electrical work includes:
Plumbing installation involves:
Ensure proper ventilation:
Read more about how long kitchen remodels take
Timeline: 1-2 days for each inspection
Multiple inspections ensure your remodel meets Portland building codes and safety standards. Plan your construction schedule around required inspections to avoid delays.
The rough inspection occurs after electrical and plumbing installation but before insulation and drywall. Inspectors verify:
Ensure inspection readiness:
Timeline: 3-4 weeks
Finish work transforms your kitchen from construction site to functional space. This phase requires careful sequencing to prevent damage and ensure quality installation.
Timeline: 1-2 weeks
Final details bring your kitchen to completion and ensure everything functions properly. This phase includes appliance installation, finish work, and project cleanup.
A kitchen renovation temporarily disrupts your normal routine, but proper preparation makes this phase manageable. Planning ahead for the inconvenience reduces stress and helps your family adapt to temporary changes.
Create a functional temporary kitchen space:
Adapt your meal planning to limited cooking facilities:
Establish clear communication protocols:
Minimize disruption to other areas:
Even with perfect planning, kitchen remodels can encounter obstacles. Understanding potential challenges and their solutions helps you prepare mentally and logistically for your renovation.
Some of the most common kitchen remodeling challenges include delays change orders, materials not arriving on time, or contractors getting busy with other projects. At Lamont Bros. we pride ourselves on routinely completing projects within 2 days of their scheduled completion date.
Going over budget is another common frustration for homeowners. We avoid this by designing beautiful, but realistic, projects our build team will be able to complete within the budget you specify. By thoroughly vetting the entire scope of the project up front, we reduce the bad surprises that can come with remodeling.
Lastly, communication can be a challenge. Working with multiple contractors, and getting those contractors to talk to one another, is a headache. At Lamont Bros. every project has a dedicated superintendent who only works on that project. They're at your home everyday, working alongside a small team to complete your remodel.
Want to discuss your project timeline? Schedule a consultation with our team to plan your kitchen remodeling journey.
A typical kitchen remodel takes 8-12 weeks from start to finish, depending on the scope of work and complexity. Here's the breakdown:
Factors that can extend the timeline include custom cabinet orders, permit delays, structural surprises, and material availability.
The kitchen remodel process involves five main phases:
Each phase requires careful coordination and typically follows this sequence to ensure proper installation and code compliance.
Kitchen remodel costs in Portland typically range from $25,000-$75,000 for a full renovation, depending on:
Always budget an additional 20% for unexpected expenses like plumbing relocations or electrical upgrades.
Most kitchen remodels in Portland require permits, especially if you're:
Permit approval typically takes 2-4 weeks in the Portland area. Your contractor should handle the permit application process and ensure all work meets local building codes.
To prepare for your kitchen remodel:
Before construction starts:
During construction:
Financial preparation:
Yes, most homeowners stay in their homes during kitchen remodels, though it requires preparation and patience.
Tips for living through the remodel:
The inconvenience is temporary, but staying in your home saves on relocation costs and allows you to monitor progress daily.
Spring and fall are ideal seasons for kitchen remodels in Portland because:
Avoid summer if possible, as it's peak construction season with higher costs and longer wait times for contractors.
When selecting a contractor:
Essential qualifications: