How Long Does It Take to Build an ADU?

Joseph Patrick Joseph Patrick
November 24, 2026
ADU

Four attached ADU projects built by Lamont Bros. took an average of about 11 weeks to construct. The projects ranged from an interior conversion completed in approximately 7.5 weeks to an addition that took about 16 weeks.

Construction is one part of the ADU timeline. Before work starts, your project needs a design, permits, and a place on the construction schedule. After the build, required final inspections and any remaining corrections determine when the space is ready to occupy.

If you are planning an ADU for a parent, an adult child, or a future tenant, knowing how those stages fit together can help you plan for the day someone moves in.

Key Points

  • Four past Lamont Bros. attached ADU projects averaged about 11 weeks of construction.

  • The three additions in that group averaged about 12 weeks of construction.

  • Design, permitting, and construction scheduling take place before the build begins.

  • A garage or basement conversion is not automatically faster than a detached ADU. Existing conditions and utility work can change the scope.

  • Final inspections and any required corrections are part of preparing the ADU for occupancy.

What Does the Full ADU Timeline Look Like?

An ADU project usually begins with a conversation about your goals and a review of your property. Your team develops the design, prepares plans for permits, and coordinates the construction schedule. Once the required permits are issued and the project is ready to start, construction begins.

Home Addition In process

Inspections take place at various points during the build. Near the end, the team completes remaining work and schedules final inspections. The time between the last stretch of construction and occupancy depends on the approvals your project needs and any corrections that come up.

When discussing timing with a builder, ask for the full schedule as well as the construction estimate. That way, you can plan for the months before crews arrive, not just the time they spend at your property.

How Long Does ADU Design Take?

The design schedule depends on the property, the decisions you need to make, and the complexity of the project. A conversion inside an existing home presents different questions from a new structure in the backyard.

Early conversations focus on how the ADU will be used. A parent who wants to age in place may need a different entrance, bathroom, and layout from a long-term tenant. Your budget, desired completion date, and the privacy you want between the ADU and the main home also shape the design.

The team then looks at the property itself. Access, drainage, utility locations, prior permit records, and the condition of an existing structure can all affect what is practical to build. Some projects may also need surveying or engineering. The location of trees, slopes, and utilities can influence how an ADU is designed for your property.

Once those questions have been explored, the design develops into drawings and specifications for pricing and permit submission. Revising the layout or adjusting the scope to fit the budget is a normal part of planning, although it can add time.

If you are weighing your options, start by comparing an ADU attached to your home with a separate backyard unit. Privacy, access, disruption, and the space available on your property all matter alongside the schedule.

How Long Does ADU Permitting Take?

Permit timing varies by city or county, the scope of the project, and the completeness of the application. After plans are submitted, reviewers may request corrections or additional information before a permit can be issued.

Ask your project team which permits and reviews are expected and how they will keep you informed. It is also worth discussing how the team will respond to review comments, since both the review and the response affect the calendar.

Permitting an ADU in Portland

In Portland, an ADU needs a building permit, along with the applicable electrical, plumbing, and mechanical trade permits. That applies to a new ADU as well as a conversion within a house or garage.

When a city reviewer needs changes or more information, they issue a check sheet. The project team responds and resubmits the requested material so review can continue. Once the permit is ready, required fees must be paid before it is issued.

Portland also offers pre-approved plans for some detached ADUs. They can provide a starting point for the building design, but the project still needs a permit application and review of the property-specific work.

How Long Does ADU Construction Take?

Construction on four past Lamont Bros. attached ADU projects took between approximately 7.5 and 16 weeks. The group included three additions and one interior conversion, with an average construction time of about 10.7 weeks. The three additions averaged about 12 weeks.

Each project had a different scope. The interior conversion was the shortest at about 7.5 weeks, while the longest addition took about 16 weeks and included new footings, walls, and a slab.

We also reviewed a new-build project that took about 12.5 weeks and a garage conversion that took about 9.5 weeks. The garage already had sewer and power, an advantage that another property may not have.

These examples show how much the work can vary from one property to another. Once your design and scope are developed, your construction team can prepare a schedule for your project.

To see what a finished backyard home can look like, take a look at this two-story ADU Lamont Bros. built for a Portland family.

ADU-1

What Happens During Final Inspections?

Final inspections are part of the last stretch of the project. Once the work is ready, the contractor schedules the required inspections. If an inspector identifies an issue, the team makes the correction and arranges another inspection when needed.

In Portland, all permits need a final approval inspection to be complete. An ADU may look ready for furniture before every approval is in place, so ask your project team what needs to happen before someone can move in.

How Does the ADU Type Affect the Schedule?

Detached ADUs

A detached ADU is a separate building, often located in the backyard. It generally needs a foundation and exterior shell, along with utility connections across the property.

The condition of the yard can have a significant effect on the work. A slope, limited access for equipment, trees, drainage needs, or a long utility route may require more planning and site preparation. The team needs to assess those conditions before giving you a useful construction schedule.

sellwoodadu-1-2

For more on planning a backyard home, explore the design and site considerations for a detached ADU.

Attached ADUs and Additions

An attached ADU can be a new addition or a dwelling created within the existing house.

An addition must connect to the home, which may involve structural changes and careful sequencing where the two meet. Depending on the scope, construction can affect the main house while your family continues to live there.

Creston-ADU-NON-1-1-1024x683-1

The three additions in our project review averaged about 12 weeks of construction, but the individual projects differed. An estimate for your home should reflect the size of the addition, the existing structure, and the work needed to connect the two.

Garage Conversions

A garage conversion may make use of existing walls and a roof, but a garage is not necessarily ready to function as a dwelling.

The slab or foundation, insulation, drainage, utilities, and structural components may all need attention. Some garages have convenient utility access; others need more extensive work before interior construction can begin.

PortlandGarageAfter

Those conditions affect both timing and the cost of turning a garage into an ADU. Looking at them early can help you decide how much of the existing structure is practical to reuse.

Basement ADUs

A basement can provide space within the home’s existing footprint, which may appeal to families who want to preserve the yard or keep a relative close.

Before it can become an independent dwelling, the space needs a careful evaluation. Ceiling height, stairs, moisture, ventilation, emergency escape, and plumbing can all affect the work. Below-grade drainage or structural changes may add time that was not obvious when the project began.

Hawthorne Basement ADU

A previously finished basement should not be assumed to be approved as an independent dwelling. If you are considering this option, learn more about creating a basement apartment in Portland.

What Can Help an ADU Project Move Faster?

No team can remove every uncertainty from an ADU schedule. Good planning can, however, reduce the time lost to unanswered questions, late changes, and work that has to be redone.

Start by sharing the date you hope to need the space. If a parent plans to move in after a particular life event, that date helps your team work backward through design, permits, construction, and final approvals. If the timing is firm, consider a backup housing plan as well.

Early property research is another valuable step. Knowing where utilities run, how crews will reach the work area, and what condition an existing structure is in can prevent the team from spending weeks developing a design that later needs to change.

It also helps to make budget and design decisions together. An ADU may be small, but it still contains many of the systems and spaces of a home. Agreeing on priorities early gives the team a clearer basis for design and pricing. 

If you plan to borrow for the project, talking with a lender during design can also help you plan how you’ll finance the ADU alongside the scope and budget.

Finally, ask when selections are needed. Fixtures, finishes, and other products may have different lead times, and a late change can affect the construction sequence. A complete permit application and timely responses to reviewer comments can also help keep the process moving, although they cannot guarantee a particular review time.

Frequently Asked Questions

Does an 11-Week Construction Schedule Mean My ADU Will Be Ready in 11 Weeks?

Not from the beginning of planning. The approximately 11-week average came from construction on four past attached ADU projects. Your project will also need time for design, permits, construction scheduling, and final approvals.

Can a Garage or Basement ADU Be Finished Faster Than a Detached ADU?

Sometimes. Existing walls or a foundation may reduce new construction, but structural repairs, moisture control, utility upgrades, and other requirements can offset that advantage. The best comparison uses schedules based on the work each option would require at your property.

Does a Pre-Approved Plan Eliminate Permit Review?

No. A pre-approved plan may address portions of the building design, but it does not necessarily cover your site or eliminate the need for a permit. In Portland, an application is still required, along with review of property-specific requirements and other applicable permits.

Can Construction Begin While the Permit Is Under Review?

Do not assume it can. Discuss the exact work and required approvals with your contractor and local permitting office before starting. Portland directs applicants to obtain the ADU permit before construction or conversion.

When Should I Start if a Family Member Needs the ADU by a Certain Date?

Start the conversation early enough to account for design, permits, construction scheduling, the build, and final approvals. Share the date with your team before design begins so you can discuss a realistic schedule and a backup plan if needed.

Make a Plan for Your ADU

A construction average can give you a reference point, but your property and goals will determine the work ahead. The next step is to look at the space available, your budget, and the date you hope to have the ADU ready.

If you are considering an ADU in the Portland area, Lamont Bros. can talk through the options with you. Learn more about how Lamont Bros. designs and builds ADUs, then bring your questions and ideas to a conversation with our team.

Joseph Patrick
Joseph Patrick

Co-Founder & CEO of Lamont Bros. Design & Construction
Joseph Patrick is the co-founder and CEO of Lamont Bros. Design & Construction. As Lamont Bros.’ principal designer for many years, he has led the design of custom homes, major additions, and high-end remodels throughout the Portland area, with multiple awards, design accolades, and magazine mentions.

Read full bio